steel Buildings

Let us take your home from concept to reality! Our team understands shop houses and barndominiums, because it’s all we do!

WHY STEEL?

While our floor plans can be built using any construction method, many of our customers choose steel when it comes to their structure. Here’s a few reasons why steel may be a great choice for your project!

The Process

Leverage our direct-to-manufacturer relationships to custom fabricate your steel-building home!

plans icon

Decide on your floor plan

Search our library of stock plans, have us design something custom, or bring your own floor plans! Stock plans are delivered same-day, custom plans typically take 4-6 weeks start to finish.

consultation icon

Consultation

There are so many variables that can affect price, aesthetic, functionality etc. Once you’ve decided on a floor plan, we’ll have an initial consultation where we will gather additional info and fine tune your building design.

bid icon

Bid

In this phase, we will take your plans and engineered load considerations to our manufacturers to provide you with a bid, including a break down of your roof, wall panel, primary and secondary steel costs. During this time, we also can provide an estimate for things like doors, windows, and insulation. Expect about 7-10 days for this phase.

approval icon

Accepting a Bid

Should you choose to move forward with the bid from one of our manufacturers, you'll be required to place a deposit with the manufacturer (usually 25%-40% of the total project cost) to begin manufacturing. The remainder is typically due at completion, prior to shipping.

engineer icon

Engineering

Each building is engineered for factors such as seismic, snow and wind loads specific to your area, and other structural components. The engineering phase takes approximately 4-6 weeks on average

building icon

Manufacturing

Current lead times for this phase are averaging 4 months (depending on the time of year and complexity of the project). During this time, your building is being produced at one of our manufacturer's factories in the U.S.

shipping icon

Shipping

When your building is ready to ship, you'll pay your final balance and receive a delivery day. Most customers elect to offload their own building, and your manufacturer will coordinate with you as to what equipment you need to have on site to do so.

house icon

Assembly

Your building arrives ready to assemble! Many customers choose to DIY their build, which is super doable! Or, you may elect to hire a contractor to erect your steel building for you. We have a number of resources, and are available to answer any questions you have about assembling your custom metal building!

The Team You Can Trust With Your Home

We are proud to work with the nation’s leading manufacturers to offer metal building systems with exceptional quality, durability, and construction. Our in-house design and engineering team is able to take your plans and turn them in to a reality, with quick turn around times, and some of the most competitive pricing in the industry. Our manufacturer relationships across the U.S allow us to affordably produce and ship your metal building, without having to sacrifice quality. As a family owned business, our reputation is everything, and we take great pride in being able to offer the best metal building solutions to our customers.